What are resources in MS Project?
a.People
b.Supplies
c.Facilities
d.All the above
What does the "Max Units" denote on the Resource Sheet?
a.The availability of the resource for project work
b.The maximum amount of resource usage for the day
c.The maximum amount of resource usage for the project
d.The availability of time per resource, per day
What is one purpose of the Resource Calendar?
a.Enter resources for the project
b.Set up non-working times for the entire project
c.View the overall project schedule
d.Assign non-working time to a resource
How are resources assigned to a task?
a.They are chosen from the Task Form dropdown
b.They are chosen in the Resources tab
c.They are chosen from the Data group
d.They are assigned in the Project Resources tab
How are resource assignments visually shown in the Gantt Chart?
a.Resource icons appear next to resource names
b.Red "stick man" icons appear in the Indicators column
c.Resource names appear next to the duration graph