Answer :
Answer:
b) process b
Step-by-step explanation:
You have 2 of machine A, each of which can do its process in 1 minute; 1 of machine B, which takes 2 minutes to do its process; and 3 of machine C, each of which takes 3 minutes to do its process.
Production quantities
In 6 minutes, the 2 of machine A can produce 2 × 6/1 = 12 units.
In 6 minutes, the 1 of machine B can produce 1 × 6/2 = 3 units.
In 6 minutes, the 3 of machine C can produce 3 × 6/3 = 6 units.
Process B produces the fewest units in equivalent time, so process b is the bottleneck.
__
Additional comment
The production quantity of a given machine is ...
(production time)/(time/unit) = units
This will be multiplied by the number of machines doing the process.
For comparison purposes, we used a production time of 6 minutes here.