Answer :
Since the projects are mutually exclusive, only one project can be accepted Accept Project B and reject Project A because Project B has higher NPV
Since the payback period and IRR is being met by both, Project with a higher NPV must be selected for higher value addition.
Mutually special tasks are capital tasks that compete without delay with each different.
For instance, if a supervisor has to make a desire strictly between challenge either assignment X or Y, however not each of them simultaneously, then initiatives X and Y are stated to be at the same time specific.
The difference among together extraordinary and impartial events is: a jointly exclusive event can absolutely be described as a scenario when occasions can not arise at an identical time whereas an unbiased occasion takes place whilst one event remains unaffected via the incidence of the opposite event.