Mary is planning her wedding and develops the following preliminary information.

Immediate Estimated

Activity Predecessor Normal Time

A (select wedding date) none 3 week

B (select wedding location) none 4 weeks

C (guest list, whose attending) A, B 4 weeks

D (select entertainment) A 3 weeks

E (choose catering) A, C 2 weeks

F (wedding day) D, E 0 weeks

a. Draw the network for this project.

b. What is the critical path(s)?



Activity

Immediate Predecessor

Time

(weeks)

Earliest

Start

Earliest

Finish

Latest

Start

Latest Finish



Slack

A

---

3

0

3

1

4

1

B

---

4

0

4

0

4

0

C

A, B

4

4

8

4

8

0

D

A

3

3

6

7

10

4

E

A, C

2

8

10

8

10

0

F

D, E

0

10

10

10

10

0


c. What is the project completion time?

d. What activity has the most slack?

e. What wedding activities did Mary leave out of her analysis? List them and now redraw the project network (but do NOT try to assign activity times or work out the new solution). What did you learn?