Answer:
c. 246 units
Explanation:
Daily demand, d = 20 units
Service Level = 95 % = 0.95. Z (according to Standardized Normal Curve) = 1.65
Average Lead Time, LT-bar = 9 days
Standard deviation of Lead Time, σLT = 2 days
Reorder Point = Expected Demand during Lead time + Safety Stock
Reorder Point = d*LT-bar + z*d*σLT
Reorder Point = (20*9) + (1.65*20*2)
Reorder Point = 180 + 66
Reorder Point = 246 units