A Program Technician is tasked with setting up a meeting. There are several responsibilities involved with this task. These are listed below along with the amount of time associated with completing each task. Setting up audio visual equipment: 30 minutes Collating and stapling meeting materials: 55 minutes Setting up chairs and tables: 115 minutes Ensuring room complies with the Americans with Disabilities Act (ADA) requirements: 50 minutes

If the Program Technician begins her task upon arriving to the office at 8 a.m., when will the room set up be completed, if she is allowed a 15 minute break at 10:00 a.m., another at 2:00 p.m., and a half hour lunch break at noon?

A. 12:35 p.m.

B. 12:55 p.m.

C. 2:00 p.m.

D. 2:15 p.m