Accounting department of “NERDS” company has 120,000 hours of work to complete for the next year.80,000 hours can be completed in the first 8 months, then the remaining 40,000 hours must be completed in the last 4 months. Company plans to add freelancers to handle the additional work in the last 4 months. A Freelancer works 200 hours per month. Approximately how many freelancers will company need to hire?
*
5 points