Using the priority list T4, T2, T5, T3, T7, T1, T6, schedule the project below with two processors.
T1 (9)
T2 (12)
T3 (10)
T4 (3)
T5 (6)
T6 (7)
T7 (8)
End
[Graphs generated by this script: setBorder(60,30,60,30);initPicture(0,3,0,2); fontsize=14;fontstyle='none';marker="arrow";line([0,2],[1,2]);line([0,2],[1,1]);line([0,1],[1,1]);line([0,0],[2,1]);line([1,2],[2,2]);line([1,2],[2,1]);line([1,1],[2,2]);line([1,1],[2,1]);line([2,2],[3,1.5]);line([2,1],[3,1.5]);fontbackground='white';fontfill='blue';text([0,2],'T1 (9)','aboveleft');dot([0,2]);fontfill='blue';text([0,1],'T2 (12)','belowleft');dot([0,1]);fontfill='blue';text([0,0],'T3 (10)','belowleft');dot([0,0]);fontfill='blue';text([1,2],'T4 (3)','aboveleft');dot([1,2]);fontfill='blue';text([1,1],'T5 (6)','belowleft');dot([1,1]);fontfill='blue';text([2,2],'T6 (7)','aboveright');dot([2,2]);fontfill='blue';text([2,1],'T7 (8)','belowright');dot([2,1]);fontfill='blue';text([3,1.5],'End','aboveright');dot([3,1.5]);]
List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then T4 then T7, enter: 1,4,7. Ignore idle time.