A project manager is in the Control Scope process of monitoring the status of the project and product scope, maintaining control over the project by preventing overwhelming scope change requests and managing changes to the scope baseline. Which one of the following is NOT true about this process?
Group of answer choices
Work performance information and Change Requests are the key deliverables in this process.
Variance analysis is used as a tool and technique in this process.
It should be performed prior to scope planning.
The Control Scope process must be integrated with other control processes