Suppose it is now the end of the seventh day and that activities a and b have been completed while activity d is 50 percent completed. time estimates for the completion of activity d are 5, 6, and 7. activities c and h are ready to begin. determine the probability of finishing the project by day 24 and the probability of finishing by day 21. (round your intermediate calculations to 3 decimal places and final answers to 4 decimal places. )



Answer :