A project ha following time chedule: Activity Time in Week Activity Time in Week 1-2 4 5-7 8 1-3 1 6-8 1 2-4 1 7-8 2 3-4 1 8-9 1 3-5 6 8-10 8 4-9 5 9-10 7 5-6 4 Contruct the network and compute: (1) TE and TL for each event (2) Float for each activity (3) Critical path and it duration