Consider the following project: Activity Immeadiate Predecessors Durations (weeks) A - 5 B A 3 C A 2 D B 3 E C 7 F B , C 3 G D , E 6 H C 2 Which one of the following would expedite the project?
Activity Immeadiate Durations
Predecessors (weeks)
A - 5
B A 3
C A 2
D B 3
E C 7
F B , C 3
G D , E 6
H C 2
Multiple Choice
Expediting D by 1 week
Expediting G by 1 week
Expediting F by 1 week
Expediting H by 1 week