The following data are average times per order over the last month.Wait time to start production 16.2 daysInspection time 1.8 daysProcess time 2.7 daysMove time 2.6 daysQueue time 8.2 daysThe manufacturing cycle efficiency (MCE) would be closest to:A. 29%.B. 82%.C. 46%.D. 18%.E. None of the above