Department B had 3,000 units in Work in Process that were 25% completed at the beginning of the period at a cost of $12,500. 13,700 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 1,700 units were 95% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710.
The number of equivalent units of production for the period for materials if the first-in, first-out method is used to cost inventories was:
a. 16,700
b. 12,000
c. 1,700