an engineering company was awarded a project with an original budget of 160,000 hours, valued at $15,000,000. the client has asked the project to prepare an in-depth analysis of the project performance and make a formal presentation. use the following data to prepare the reports and presentation as requested by the client. planned hours 65,000 actual hours spent to date 73,000 % complete 40% what many hours have the project earned?



Answer :