The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and slack times. Identify the critical path.

ID Description Predecessor Time

A Order Review None 2

B Order Standard Parts A 3

C Produce Standard Parts A 10

D Design Custom Parts A 13

E Software Development A 18

F Manufacture Custom Hardware C, D 15

G Assemble B, F 10

H Test E, G 5