A masonry contractor is preparing an estimate for building a stone wall and gate. He estimates that the job will take a
40-hour work week. He plans to have three laborers at $15 per hour and four masons at $25 per hour. He'll need $3268
worth of materials and wishes to make a profit of $700. Write a mathematical statement that will give the estimated cost of
the job. Then calculate this total.
Select the correct choice below and fill in the answer box to complete your choice.