The formula below is often used by project managers to compute EEE, the estimated time to complete a job, where OOO is the shortest completion time, PPP is the longest completion time, and MMM is the most likely completion time.
E=\dfrac{O+4M+P}{6}E=
6
O+4M+P

E, equals, start fraction, O, plus, 4, M, plus, P, divided by, 6, end fraction
Which of the following correctly gives PPP in terms of EEE, OOO, and MMM



Answer :

The equation which correctly gives P in terms of E, O and M as required is; P = 6E - 4M - O.

Change of formula subject

It follows from the task content that the expression which represents P in terms of E, O and M be determined.

On this note, since the initial formula is;

E = (O + 4M + P)/6

Multiply both sides by 6;

6E = O + 4M + P

Subtract O and 4M from both sides;

P = 6E - 4M - O.

Read more on change of subject;

https://brainly.com/question/343660