Consider the order‑requirement digraph.
Find the earliest completion time and the new critical path if task T5 is reduced to time length 7.
Give the earliest completion time as a whole number.
earliest completion time:
——————————————————-
What is the new critical path?
A. T1T4T7
B. T1T5T7
C. T2T5T7
D. T3T6T7