Consider the following information carefully and do as per the instruction given under the table below.
ACTIVITY Immediate Predecessor Duration (in weeks)
A - 6
B - 8
C A 2
D A 6
E B,C 5
F B,C 5
G D,E 4
H F 2
I G,H 4
Required:
A. Draw the network diagram of this project