The critical path of a project includes 45 business days in phase one, 20 business days in phase two, 15 business days in phase three, and 10 business days in phase four. the workforce is expected to work six days per week. if the project needs to be complete by, if the project started on 2nd january, when is the deadline? do not include any holidays or employee time off.